Track procurement packages and lead times

Short answer: Switch on Procurement in Profile & settings → Optional modules, then open More → Procurement. Add the packages the schedule depends on with their required, promised and delivery dates; PVology shows which are late or at risk.

Verified for PVology 0.30.0 · updated 2026-10-08

Steps

  1. Open the project, choose Profile & settings and switch on Procurement under Optional modules.
  2. Open More → Procurement and choose Add a package for materials, equipment and subcontracts with lead times.
  3. Enter the planned order date, the required date and, once known, the promised and delivered dates.