How to link activities with logic (predecessors and successors)

Short answer: On the Schedule tab use Add a logic link: enter the Predecessor ID and Successor ID, choose FS, SS, FF or SF and an optional lag, then choose Add link.

Verified for PVology 0.19.0 · updated 2026-10-06

When to use this

You want activities to follow each other so PVology can calculate dates and the critical path.