Control accounts and estimate-at-completion methods
Short answer: Open the project's Cost page and choose Control accounts to split the budget into parts someone owns; budget moves only through recorded movements. On the Cost page, choose how the estimate at completion (EAC) is worked out; each method shows its formula.
Verified for PVology 0.30.0 · updated 2026-10-08
Steps
- Open the project, choose Cost and then Control accounts. Create an account (for example 01-CIVIL) with its owner.
- Use Record a budget movement for approved changes, transfers between accounts or contingency draws. Movements are never edited; record a reversing movement to correct one.
- Book costs and commitments against an account on the Cost page.
- On the Cost page, under the forecast, choose how the estimate at completion is worked out:
Current cost performance continues: EAC = BAC ÷ CPI.