ProjectOrbit: Project Management Foundations
Plan, run and close a project that delivers its intended outcome: lifecycle choice, charter, scope and WBS, schedule and critical path, budget and baseline, risk, quality, change control, reporting and handover.
Leads to the PVology Certified ProjectOrbit Associate (PCOA) after you pass the exam, your practical work is approved and the Academy approves the result.
A PVology credential: not issued, accredited or endorsed by PMI, ISO, SAVE International or any other body.
Who it is for
People starting to lead or support projects in any sector, and specialists who want a structured foundation.
Prerequisite: A verified PVology account. No prior certification is required.
Learning effort: about 25 hours, calculated from the authored lessons, activities and checks.
Case study: Harbor Clinics patient-booking system. Harbor Clinics is a fictional group of eight outpatient clinics. All people, figures and datasets are invented for teaching.
Syllabus
Module 1. Projects, outcomes, value, ethics and the project environment
- 1. What a project is, and why outcomes and value matter more than outputs · about 40 minFree preview
- 2. Framing Harbor Clinics with the PVology Value Lens · about 42 min
- 3. Applying the frame: environment scan and ethical judgment · about 40 min
Learning outcomes
- Distinguish a project from ongoing operations using the tests of temporary effort, unique result and defined end
- Classify statements about a piece of work as outputs, outcomes or benefits
- Explain how internal and external environment factors shape a project before it starts
- Describe four ethical duties a project lead owes to sponsors, team members and the public
- Apply the five steps of the PVology Value Lens (Need, Function, Outcome, Alternatives, Value) to a proposed project
- Calculate the monthly and annual cost of a performance problem from stated assumptions
- Draft measurable outcome statements with a baseline, a target and a time frame
- Compare alternatives by the functions they deliver before comparing their cost
- Draft an environment scan with internal and external factors and an action for each
- Classify ethical dilemmas against the duties of responsibility, respect, fairness and honesty
- Justify a recommended response to a conflict of interest or pressure to misreport
Module 2. Lifecycle selection: predictive, agile and hybrid approaches
- 1. Lifecycles and delivery approaches: what they are and when each fits · about 40 min
- 2. Worked example: a suitability score for each part of Harbor Clinics · about 42 min
- 3. Applying lifecycle choice: justify, challenge and adjust · about 40 min
Learning outcomes
- Describe the phases of a project lifecycle and the purpose of phase gates
- Compare predictive, iterative, incremental, agile and hybrid approaches by how they handle uncertainty and change
- Classify project characteristics that favour predictive or adaptive delivery
- Calculate a delivery suitability score for each component of a project using six weighted factors
- Classify each component as predictive, hybrid or agile from its score and justify any override
- Draft a hybrid delivery outline with a master schedule, iteration plan and integration milestones
- Justify a lifecycle recommendation to a sponsor using named factors and their consequences
- Compare the cost of discovering a requirement error early versus late under different approaches
- Critique a lifecycle decision and propose a specific adjustment
Module 3. Business case, charter, objectives, success criteria and governance
- 1. Business case, charter and governance: what each one is for · about 40 min
- 2. Worked example: the Harbor Clinics business case and charter · about 45 min
- 3. Applying it: draft a charter and test the business case · about 42 min
Learning outcomes
- Distinguish the purpose, owner and content of a business case and a project charter
- Draft project objectives that are specific, measurable and time-bound
- Classify success criteria as measures of project delivery or of outcome and benefit
- Describe governance roles, decision rights, tolerances and escalation routes for a small project
- Calculate net annual benefit, simple payback and a five-year benefit-cost ratio from stated assumptions
- Test a business case's sensitivity to its most uncertain assumption
- Draft charter objectives, success criteria and tolerances consistent with the business case
- Calculate payback and benefit-cost ratio for a process-improvement project, stating capacity assumptions
- Draft a one-page charter with measurable objectives, success criteria, governance and tolerances
- Critique a draft charter and justify specific corrections
Module 4. Stakeholders, communication, team responsibilities and RACI
- 1. Stakeholders, engagement, communication and responsibility · about 40 min
- 2. Worked example: Harbor Clinics stakeholder and communication plan · about 42 min
- 3. Applying RACI: build, review and correct a responsibility matrix · about 42 min
Learning outcomes
- Classify stakeholders by influence and interest and record their current and desired engagement
- Describe the elements of a communication plan and calculate the number of communication channels in a team
- Explain the four RACI roles and the rules that make a RACI matrix workable
- Draft a stakeholder register with influence, interest, engagement gaps and actions for a multi-site project
- Calculate the effect of team growth on communication channels and justify a structural response
- Draft a communication plan whose methods match each purpose and audience
- Draft a RACI matrix for a project's key activities with exactly one accountable role per activity
- Critique a RACI matrix by checking rows and columns for missing, duplicated or excessive assignments
- Justify corrections in terms of decision speed, ownership and workload
Module 5. Requirements, scope, work breakdown, deliverables and acceptance
- 1. From requirements to scope and a work breakdown structure · about 40 min
- 2. Building the Harbor Clinics WBS and dictionary · about 40 min
- 3. Acceptance criteria, scope control and feedback on your WBS · about 40 min
Learning outcomes
- Classify requirements as business, stakeholder, solution (functional or non-functional) or transition requirements
- Draft a scope statement that separates in-scope deliverables, exclusions, constraints and assumptions
- Apply the 100% rule to check that a WBS level contains all of its parent's work and nothing else
- Describe what a work package and a WBS dictionary entry must contain
- Compare deliverable-based, phase-based and location-based level-1 WBS structures for a given project
- Decompose a deliverable into work packages and reconcile their estimates with a top-down figure
- Draft a WBS dictionary entry with a boundary statement, acceptance criteria and basis of estimate
- Draft measurable acceptance criteria that state the condition, the test method, the threshold and the acceptor
- Calculate whether a test result meets a percentage acceptance threshold
- Distinguish scope creep and gold plating from approved change, and route new requests correctly
- Evaluate a draft WBS against a marking rubric and improve it
Module 6. Dependencies, estimating, schedules, critical path and milestones
- 1. Dependencies, leads and lags, and estimating durations · about 40 min
- 2. Calculating the Harbor Clinics network: forward pass, backward pass and critical path · about 45 min
- 3. Applying the schedule: lags, compression and schedule quality · about 40 min
Learning outcomes
- Classify dependencies as finish-to-start, start-to-start, finish-to-finish or start-to-finish, and as mandatory, discretionary or external
- Explain the effect of a lead or a lag on the start of a successor activity
- Calculate a three-point PERT estimate using (O + 4M + P) ÷ 6 and compare it with analogous and parametric estimates
- Describe how a schedule network produces a critical path and float
- Calculate early start, early finish, late start and late finish for every activity in a small network
- Calculate total float and free float and identify the critical path
- Explain how milestones and near-critical paths inform schedule decisions
- Calculate a network that includes a finish-to-start lag and identify its critical path and float
- Compare fast-tracking and crashing as ways to shorten the critical path, including their risks
- Evaluate a draft schedule against a quality checklist and give specific feedback
Module 7. Cost estimating, budgets, baselines and basic performance measurement
- 1. Estimating cost, building a budget and understanding reserves · about 40 min
- 2. The Harbor Clinics budget, baseline and month-4 performance check · about 45 min
- 3. Applying earned value and reporting cost performance · about 40 min
Learning outcomes
- Classify project costs as direct or indirect and as labour, materials, equipment, services or other
- Calculate a budget build-up from work package estimates, contingency reserve and management reserve
- Distinguish contingency reserve from management reserve by purpose, owner and control
- Define planned value, earned value and actual cost and calculate cost and schedule variance for a simple case
- Calculate a bottom-up work package estimate and a time-phased cumulative planned value
- Calculate earned value from work package budgets and percent complete
- Calculate CV, SV, CPI, SPI and a simple estimate at completion, and interpret them for a sponsor
- Calculate PV, EV, AC, CV, SV, CPI, SPI and a simple EAC from a project status dataset
- Interpret the four combinations of cost and schedule variance and propose suitable responses
- Draft a short cost performance report that a sponsor can act on
Module 8. Risk, assumptions, issues, responses and escalation
- 1. Risks, assumptions and issues: describing, assessing and responding · about 40 min
- 2. The Harbor Clinics risk register: scoring, EMV and contingency · about 45 min
- 3. Applying risk responses, opportunities and escalation · about 40 min
Learning outcomes
- Distinguish a risk, an issue and an assumption, and explain how each is recorded and managed
- Draft risk statements in cause-event-effect form
- Calculate a probability-impact score and an expected monetary value
- Select threat responses (avoid, transfer, mitigate, accept, escalate) and opportunity responses (exploit, share, enhance, accept, escalate) and justify the choice
- Calculate probability-impact scores and expected monetary values for a set of risks and rank them
- Explain why rankings by score and by EMV can differ and what to do about it
- Link the sum of threat EMVs to a contingency reserve and decide how to treat opportunities
- Manage the transition of a risk to an issue, including contingency release
- Draft cause-event-effect statements, triggers and owners for a set of project concerns
- Calculate the net expected value of a response to a threat or an opportunity and decide whether it is worthwhile
- Justify an escalation using agreed criteria and write a clear escalation note
Module 9. Quality, procurement, resources and supplier coordination
- 1. Quality planning, assurance, control and the cost of quality · about 40 min
- 2. Procurement: make or buy, contract types and risk allocation · about 42 min
- 3. Resources, levelling and supplier coordination in practice · about 40 min
Learning outcomes
- Distinguish quality planning, quality assurance and quality control and give one project example of each
- Draft testable acceptance criteria for a deliverable
- Calculate the cost of quality in its four categories and compare conformance with non-conformance cost
- Justify a prevention investment using a cost-of-quality comparison and its stated assumptions
- Calculate a make-or-buy comparison over a stated period and identify the non-financial factors
- Compare fixed-price, cost-reimbursable and time-and-materials contracts and explain how each allocates risk
- Calculate the buyer's cost under each contract type for a given overrun scenario
- Recommend a contract type for a described situation and justify it
- Build a weekly resource histogram from task assignments and identify over-allocation
- Level a resource using available float and state the effect on the schedule
- Draft a supplier coordination plan covering cadence, interfaces and escalation
Module 10. Change control, reporting, corrective actions and delivery monitoring
- 1. Change control and baseline configuration · about 40 min
- 2. Status reporting, variance thresholds and corrective action · about 42 min
- 3. Delivery monitoring in practice: taking a change through PVology ProjectOrbit · about 42 min
Learning outcomes
- Describe the steps of a change control process from request to baseline update
- Analyse the impact of a change request on scope, schedule, cost, risk and benefits
- Classify a change as within or beyond delegated authority using stated thresholds
- Explain how baseline versions are controlled and why
- Calculate schedule and cost variances and indices and rate them against stated thresholds
- Draft a concise status report with status, trend, issues, decisions needed and forecast
- Distinguish corrective actions from preventive actions and propose one of each for a variance
- Prepare a full impact analysis with options for a substantial change request
- Recommend a change board decision and justify it against current project performance
- Record the change, decision and any baseline update using the project registers and baseline tools
Module 11. Operational readiness, handover, benefits ownership and lessons learned
- 1. Operational readiness, transition and go-live decisions · about 40 min
- 2. Acceptance sign-off and benefits ownership · about 42 min
- 3. Project closure and lessons learned · about 40 min
Learning outcomes
- Define readiness criteria across people, process, technology, data and support
- Assess readiness evidence and make a justified go, conditional go or no-go recommendation
- Draft a transition plan that covers support, fallback and hypercare
- Prepare an acceptance sign-off with evidence, open items and conditions
- Calculate the expected annual value of benefits from baseline, target and unit values
- Draft a benefit profile with owner, measure, baseline, target, data source and review dates
- Distinguish cash-releasing benefits from capacity-releasing benefits
- Complete a closure checklist covering contracts, finances, resources, records and open items
- Calculate final cost variance against the original and current baselines and explain the difference
- Write lessons learned with cause, effect, recommendation and an owner who will act on them
Module 12. Guided PVology application lab and integrated project capstone
- 1. Guided lab: building the Harbor Clinics pilot in PVology ProjectOrbit · about 45 min
- 2. The capstone brief, rubric and a fully worked model capstone · about 50 min
- 3. Capstone self-review, common mistakes and submission · about 45 min
Learning outcomes
- Enter project setup and charter information that is consistent with an approved business case
- Build a WBS and a dependency-based schedule and verify the critical path and float by calculation
- Set a baseline, record risks and a change decision, and check that the dashboard reflects the same data
- Explain each required capstone element and how it will be assessed
- Apply the five-criterion rubric to judge the quality of a capstone
- Trace the logic of a complete model capstone from charter to handover checklist
- Self-assess a capstone draft against the rubric and calculate its score
- Identify and correct the most common capstone mistakes
- Prepare a complete submission package with assumptions, calculations and a cover summary
Capstone: Plan a small implementation project: charter, WBS, schedule with critical path, budget and baseline, stakeholder plan, risk register, one change decision and a handover checklist.
Certification exam
60 questions in 90 minutes; provisional pass mark 70%. Questions are scenario-based drawn from a private, reviewed bank. Results stay provisional until academy review. These are PVology assessment policies.
| Domain | Share of questions |
|---|---|
| Initiation and value | 15% |
| Planning | 30% |
| Delivery and team | 20% |
| Monitoring, change and risk | 20% |
| Readiness and benefits | 15% |
Across the domains, about 65% of questions test professional knowledge, 20% applied tools and 15% PVology concepts.